New Delhi: Homebuyers facing long delays in real estate projects cannot claim compensation beyond the legally prescribed interest for the delay period, the Punjab RERA has clarified in a recent order.

The regulator stated that while developers are obligated to pay interest for delays in handing over possession, buyers are not entitled to additional monetary compensation unless they can prove specific financial losses caused by the delay.

What the RERA Order Said

Add Zee News as a Preferred Source

Punjab RERA observed that the Real Estate (Regulation and Development) Act, 2016, clearly defines the relief available to homebuyers in delayed projects. According to the law, interest payable for the period of delay is considered adequate compensation unless exceptional circumstances are established.

The authority rejected the buyer’s demand for extra damages, noting that general inconvenience, mental stress, or prolonged waiting cannot automatically translate into additional compensation under RERA provisions.

Interest Is the Only Statutory Relief

Under Section 18 of the RERA Act, a homebuyer has two clear options in case of delay:

Withdraw from the project and claim a full refund with interest, or

Continue with the project and receive interest for every month of delay until possession is handed over

Punjab RERA emphasized that these remedies are exhaustive unless the agreement for sale explicitly provides for higher compensation.

Burden of Proof on Homebuyers

The regulator also highlighted that buyers seeking compensation beyond interest must submit documentary evidence of actual losses, such as higher rent payments, loan penalties, or other quantifiable financial damage. In the absence of such proof, no additional relief can be granted.

Impact on Homebuyers and Developers

This ruling reinforces a growing trend among RERA authorities to strictly interpret the Act, offering certainty to developers while limiting discretionary compensation claims. For homebuyers, it underlines the importance of carefully reviewing builder-buyer agreements and maintaining records of any financial losses arising from delays.

Key Takeaway

While RERA continues to protect buyers against project delays, compensation is largely restricted to interest for the delay period, unless buyers can clearly demonstrate specific financial harm beyond the delay itself.


Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Ola Electric launches QIP to raise up to ₹500 crore; Stock down 3%

Shares of Ola Electric Mobility Ltd. declined nearly 3%...

Indian consumers turn cautious, boost savings amid economic uncertainty: Kantar survey

Indian consumers are becoming "more cautious" about their "broader...

First IAEA report on Iran’s nuclear programme since February shows little change despite war

The UN nuclear watchdog sent a report to member...

AI, Gold and Canada’s ‘Lost Status’ at Sohn Montreal

(ब्लूमबर्ग) - हेज फंड मैनेजर और अन्य निवेशक मॉन्ट्रियल...