The project involves the construction and commissioning of an approximately 250-km transmission network in Karnataka, comprising 400 kV double-circuit lines, 220 kV double-circuit lines and 220 kV underground cables.
Also read: Varun Beverages shares can rise 23%, CLSA projects on Asahi Group partnership
It also includes the establishment of a 5×500 MVA, 400/220 kV air-insulated substation (AIS) at Ryapte in Tumkur district and a 3×500 MVA, 400/220 kV gas-insulated substation (GIS) at Doddathaggalli near Hosakote, along with associated bus reactors.The transmission network will connect Ryapte, Doddathaggalli, Kolar, Ekarajapura, Hosakote and Sarjapura substations through a combination of overhead transmission lines and underground cable links.
Tata Power said the contract has been awarded by a domestic entity and does not constitute a related-party transaction.
Shares of the company were trading at the day’s lows, down almost 0.5% on Friday at ₹400.95. The stock has gained 5% this year, so far.
Also read: Zomato-backed Cult.fit revives shelved IPO, eyes up to ₹4,000 crore: Sources